Main points of construction management of large steel structure workshop

- Feb 14, 2020-

The main points of construction management of large-scale steel structure workshops are analyzed from the aspects of preparation before construction, steel structure production, and installation process, and the main points and methods of construction management of steel structure workshops are pointed out.


I. Main points of supervision (management) control during the construction preparation stage


(1) Form a project management team. According to the characteristics of the project, it is necessary to select personnel with experience, strong technical ability, strong sense of responsibility, and coordination and coordination, and professional support. In particular, the selection of directors must have good professional quality and service awareness; The function of the functional department selects a suitable supervision organization form according to the characteristics of the project.


(2) Familiar with the drawings, specifications and design requirements, preside over the drawing review and design submission; understand the construction unit, and prepare targeted supervision planning, supervision implementation rules, management plans, etc. Managers must be familiar with drawings and design ideas, master specifications and atlases, and understand the requirements of management rules. Understand the functional requirements and design intent of the steel structure, do a good job of "design check", understand the project operation system and management system of the construction unit, and urge its quality management system, technical management system, and safety management system to be implemented and checked. The employment certificate, verification of the post certificate of the main operator, a thorough investigation of the quality of the team, and specific management requirements, can only ensure the smooth progress of the project.


(3) Strengthen the inspection and review of the qualifications of subcontractors and steel structure processing and manufacturing plants. Strengthen the inspection of steel structure manufacturing plants, mainly examining the equipment capabilities, technical capabilities, process design capabilities, process flow, process inspection, inspection methods and conditions, quality management system, welding process assessment, assembly conditions, etc. The unit must propose rectification and make rectification within a time limit. The construction unit is requested to cooperate in urging the rectification and sign a qualification review report and a start-up order after the rectification is in place. It is necessary to review the quality assurance system and quality inspection system of the subcontracting unit, and check whether the self-inspection equipment and use conditions meet the requirements of this project.


(4) Carefully review the construction organization's design and construction plan of the construction unit to see if it can meet the particularity of the project, especially the hoisting plan. It should be analyzed according to site conditions, and the entry and exit and operating positions of heavy lifting equipment. Hardening, etc .; the rationality of on-site construction layout, quality, schedule, safety, construction guarantee measures under special conditions, machinery, equipment, instruments, inspection tools, etc., should be urged to rectify within a time limit if they cannot meet the requirements of this project, the supplementary technology Measures shall be implemented, process tests and appraisal opinions shall be provided for the use of new technologies, new materials and new processes, construction units shall be urged to improve and strengthen the control of various management objectives, and the responsibility system at all levels shall be implemented and effectively operated.